On the 11th April 2018, the St. Lucia Electricity Services Limited (LUCELEC) - the sole electric utility company on the island - completed the commissioning of the island''s first utility-scale solar PV plant. The plant is rated at 3 megawatt (MW) and is located in La Tourney, Vieux Fort, just north of the Hewanorra International
The solar farm is historic for Saint Lucia as it will be the first utility-scale renewable energy project on the island, where diesel-powered generators currently account for over 99% of electricity generation.
The 3MW solar farm meets about 5% of St. Lucia''s electricity demand and will reduce the volume of fuel purchased by LUCELEC by about 300 thousand gallons per year. LUCELEC uses approximately 20 million gallons of fuel per year.
The 3MW solar farm meets about 5% of St. Lucia''s electricity demand and will reduce the volume of fuel purchased by LUCELEC by about 300 thousand gallons per year. LUCELEC uses approximately 20 million gallons of
THE St. Lucia Electricity Services Limited (LUCELEC) 3MW Solar Farm in La Tourney, Vieux Fort, is now feeding solar energy into the island''s electricity grid. Energy from the nearly 15 thousand solar panels that
Castries, April 13, 2018 – The St. Lucia Electricity Services Limited (LUCELEC) 3MW Solar Farm in La Tourney, Vieux Fort is now feeding solar energy into the island''s electricity grid. Energy
St Lucia Electricity Services Ltd (Lucelec), the sole power supplier on the Caribbean Island of Saint Lucia, will start building a 3-MW solar power plant by the end of September. The company has signed an engineering, procurement, and construction (EPC) deal with solar energy firm Grupotec, Lucelec said in a press release on Tuesday.
The solar farm is historic for Saint Lucia as it will be the first utility-scale renewable energy project on the island, where diesel-powered generators currently account for over 99% of electricity generation.
On the 11th April 2018, the St. Lucia Electricity Services Limited (LUCELEC) - the sole electric utility company on the island - completed the commissioning of the island''s first utility-scale solar PV plant. The plant is rated at 3 megawatt (MW) and is located in La Tourney, Vieux Fort, just north of the Hewanorra International
Saint Lucia''s new farm is expected to contribute 15m units of electricity a year. While this amounts to just 1.3 per cent of the current output from LUCELEC''s Cul De Sac power plant, it will make the system more resilient against a single point of failure.
Castries, April 13, 2018 – The St. Lucia Electricity Services Limited (LUCELEC) 3MW Solar Farm in La Tourney, Vieux Fort is now feeding solar energy into the island''s electricity grid. Energy from the nearly 15 thousand solar panels that
Castries, April 13, 2018 – The St. Lucia Electricity Services Limited (LUCELEC) 3MW Solar Farm in La Tourney, Vieux Fort is now feeding solar energy into the island''s electricity grid. Energy from the nearly 15 thousand solar panels that comprise the island''s first utility-scale solar farm began feeding the grid on Monday, April 9, and
THE St. Lucia Electricity Services Limited (LUCELEC) 3MW Solar Farm in La Tourney, Vieux Fort, is now feeding solar energy into the island''s electricity grid. Energy from the nearly 15 thousand solar panels that comprise the island''s first utility-scale solar farm...
The three megawatt solar plant will be located north of the Hewanorra International Airport at La Tourney, Vieux Fort, and represents the first utility-scale solar PV project in Saint Lucia. The project is being funded by LUCELEC.